Important Dates:

November 9, 2017:  Application Filed for Review

December 21, 2017: Close of Public Comment Period

February 26, 2018:  Informal Public meeting (Co Springs)

March 30, 2018:  Close of Application Review Period

April 9, 2018:  Pre-Hearing Conference (Co Springs)

April 25-26, 2018:  Formal Board Hearing (Co Springs)

 

The April 25-26, 2018 Mined Land Reclamation Board hearing will begin with preliminary (i.e., Non-Hitch Rack Ranch Quarry Application) matters at 8:30 a.m.  The Hitch Rack Ranch Quarry Application hearing will begin at 9 a.m. or as soon thereafter as the matter can be considered.

 

All submittals to the Board or Division regarding the Hitch Rack Ranch Quarry should be filed by email to drms.temp@state.co.us 

 

  

The links to imaged documents on this page are links to specific document types, and do not encompass all documents on file for the Hitch Rack Ranch Quarry.  For a complete list of all documents publicly available, click here.